Water tank construction ahead of schedule

 


The new water tank construction project on Young Street is ahead of schedule by about 10 percent. That was determined at a meeting of the city, the engineer, DEQ and Wynn Construction on June 6. The current projected completion date is Aug. 28, according to Alva Business Manager Joe Don Dunham.

He reported on a meeting with representatives of Rural Water District #1 (Capron) to discuss the proposed contract with the city. RWD #1 is concerned that the proposed rate hike would put over a hundred of their field water tap customers in jeopardy. They propose a rate similar to their current one. Dun...